QNR – Senedd Cymru ar 17 Mai 2017.
We are working with Network Rail to identify cost-effective options to upgrade the Maesteg branch line for additional services.
We continue to provide the best support, infrastructure and conditions for all businesses to grow, sustain and prosper.
Due diligence, having been delayed due to the need for clarification and additional information, will be completed in the next few weeks.
Through investing in infrastructure, skills and improving general business conditions, we are promoting growth, tackling inequality and spreading opportunity.
Outline design development and environmental impact assessment is nearing completion for the scheme with publication of draft orders planned for July 2017. A public local inquiry, if required, is planned for February 2018, with construction programmed to begin towards the end of 2019.